Red brick home entrance with a black arched doorway, white-trimmed window, stone steps, and autumn foliage.

Capital Crescent Trail in Bethesda: Fall 2026 Route Updates

"We are working very hard to complete construction of the Capital Crescent Trail in spring, summer of next year," Purple Line Senior Project Director Ray Biggs II told the County Council's Transportation and Environment Committee in September 2025. At the same meeting, MCDOT's Maricela Cordova said the county's connecting projects would be done on the same schedule: "We will be ready for spring, summer of next year for sure."

Spring and summer have now passed. As of October 2026, the paved trail along the Purple Line from Bethesda toward Silver Spring is still off-limits. Fences are still up in the north half of Elm Street Park. Light-rail vehicles are running test trips into Bethesda Station. The county's own part of the work is the closest to done. It is also the part most likely to define how Bethesda reaches the trail for years. That part is a street-level path along 47th Street and through a neighborhood park. The tunnel under Wisconsin Avenue is not part of the near-term plan.

The schedule slipped. The route didn't.

The Purple Line project's FAQ still says trail construction will be "completed in 2026." It also says the finished paving so far, including the stretch between Bethesda and Connecticut Avenue, is about one-third of the total paved trail area. Montgomery County's capital budget page for the trail was updated more recently, on May 18, 2026. It now expects the main trail along the Purple Line to be finished by Spring 2027, citing MTA's current schedule.

Until then, the corridor is a work site. The MTA says construction vehicles use the trail for access and that walking and biking on it are prohibited. The project's closure list shows the Georgetown Branch Interim Trail closed from September 2017 through December 2026. On the Silver Spring side, the advocacy group Purple Line NOW reported on September 23, 2026, that the segment from the Talbot Street bridge toward the Metropolitan Branch Trail connection "is still very much a construction zone." The group tied the delay to station work and utility relocation.

Questions about the corridor are coming from residents. Councilmember Evan Glass said at that 2025 hearing that his office had received "dozens and dozens" of questions. Residents wanted to know when they could ride the Purple Line and when they could get back on the nearby trails. He described the mood as "construction fatigue."

Why the surface path is the lasting answer

The Purple Line required moving the Capital Crescent Trail at downtown Bethesda. Planners studied two ways to carry it across Wisconsin Avenue. One was a tunnel under the avenue. The other was a surface route through Elm Street Park. In October 2021, the Montgomery County Planning Board approved both. Funding for the tunnel was then pushed beyond the current funding cycle, so MCDOT went ahead with the surface route.

The tunnel has not moved closer since. MCDOT describes a passage about 1,000 feet long. It would start on the west side of 7272 Wisconsin Avenue, run under Wisconsin Avenue and Elm Street, and come out at the surface trail in Elm Street Park. The tunnel's FY27 capital budget sheet lists it at final design with projected costs of $82.545 million. All of its scheduled funding and spending falls beyond the six-year budget window. The same sheet puts bid documents, utility relocation and construction beyond six years as well.

That timing makes the surface route Bethesda's trail connection for the foreseeable future. MCDOT's alignment runs along the north side of Bethesda Avenue to Wisconsin Avenue. It continues along the south side of Willow Lane to 47th Street, then follows a shared-use path on 47th Street to Elm Street Park. From the park, the trail heads north to meet the future Purple Line trail. The Town of Chevy Chase says that connection will be beneath the Bethesda Crossing building.

Where things stand this month

Piece of the corridor Status as of October 1, 2026 Next milestone
47th Street shared-use path, Phase 2 About 90% complete Completion forecast for October 2026
Elm Street Park north section, Phase 3 Closed to the public since September 4 Park renovation completion in 2027
Purple Line trail, Bethesda to Silver Spring Closed; used for construction access County expects construction done by Spring 2027
Wisconsin Avenue trail tunnel Final design Funded only beyond the six-year capital budget
Bethesda Market Park Preliminary planning Design and construction dates listed as TBD

The 47th Street segment is the next piece to finish. Montgomery Parks' September 16 update put it at about 90% complete and forecast completion this month. No opening announcement had been posted as of October 1. The county's budget page had originally scheduled this segment and the link through Elm Street Park for fiscal year 2026. The Town of Chevy Chase lists what Phase 2 includes: the shared-use path along 47th Street, a park entry plaza, sidewalk upgrades, lighting and new trees.

Phase 3 has already started. MCDOT's project page recorded tree clearing and silt-fence work on September 28. The part of Elm Street Park north of Elm Street is closed to the public during construction. The Town points families to Leland Park at 4300 Elm Street as the nearest open playground and basketball court.

The rail line itself is in testing nearby. Purple Line crews are running a light-rail vehicle between the Lyttonsville Operations and Maintenance Facility and Bethesda Station. Most testing happens between 7 a.m. and 7 p.m., but the project says vehicles could move at any hour. The test runs stay on dedicated Purple Line tracks and do not cross traffic.

Getting onto the open trail from Bethesda Avenue

The trail toward Georgetown is open. Its northern trailhead is currently at the junction of Bethesda Avenue and Woodmont Avenue, two blocks west of Wisconsin Avenue. The Coalition for the Capital Crescent Trail gives these landmarks for the start:

  1. The crossing at Bethesda and Woodmont does not run straight across. The Coalition places the Georgetown-bound trail between public parking Lot 31 and Ourisman Honda.
  2. County Parking Garage 57 is on the north side of Bethesda Avenue, less than a block west of the trail.
  3. Ourisman Plaza sits beside the dealership. A rest area with a trail map and water is just behind it, a few hundred feet south of Bethesda Avenue.
  4. Griffin Cycle, at 4933 Bethesda Avenue, is on the Coalition's bike-shop list, two blocks west of the trail.

Two Bethesda Row stops are along the same stretch. Bethesda Bagels is at 4819 Bethesda Avenue and Quartermaine Coffee is next door at 4817.

Crossing the Purple Line work zone on foot still takes a detour. Pedestrian access between Wisconsin Avenue and Elm Street remains closed. The posted route uses the Wisconsin Avenue crossings at Elm Street and Waverly Street, then goes west on Hampden Lane to Woodmont Avenue and back to Elm Street. That notice covers pedestrians only. The project tells everyone to follow on-site signs and stay out of the work zone.

The Georgetown end has its own detours

A ride south from Bethesda runs into construction at the other end too. The National Park Service says the trail from the Maryland–D.C. line to the Water Street trailhead remains open. NPS rehabilitation work is expected to start in phases in 2027.

Near the river, DC Water is building a sewer overflow project and has moved the trail more than once. In January 2026, it opened a temporary cycling path through Georgetown Waterfront Park between 33rd and Potomac streets. It also set up a pedestrian detour along the riverfront between 34th Street and Cecil Place, with work there scheduled from January 2026 through 2030. A May 5 notice described another temporary route around the aqueduct work zone, planned to open about May 6. It shifted access north and warned of drilling noise. Back in March 2025, the Coalition had warned that this work could affect trail users for up to five years. Because the routes have changed during construction, posted signs are the best guide on any given day.

What the finished Elm Street corner will hold

Elm Street Park is a two-acre park at 4600 Elm Street. It sits inside Town of Chevy Chase limits and is maintained by Montgomery Parks. The trail will run through it, and the Phase 3 plans reflect that. The new design includes wide trail crossings with clear sight lines and protective fencing between the play areas and the trail.

The park will have two playgrounds with a cork-based poured surface. The eastern one, for ages 2 to 12, includes an enclosed swing with harness, a low-floor spinner and a treehouse with a 4-foot slide. The middle play area, for ages 5 to 12, adds 8-foot and 15-foot climbing towers and a rope tunnel. A fitness zone for ages 13 and up includes a calisthenics rack and the "Ocean Ring." The promenade gets new paving, lighting, a drinking fountain and infrastructure for community events.

Montgomery Parks designed the equipment to be different from what is planned for Bethesda Market Park next door. That park is still in preliminary planning as of the August 18, 2026 update, and its design and construction dates are listed as TBD. The plan would turn two parking lots into park space. Together with Elm Street Urban Park, that would add up to about four acres of downtown parkland.

The 47th Street path is forecast to finish this month and the Elm Street Park work in 2027. Both are on firmer schedules than the Purple Line trail behind them or the tunnel that was once the alternative.

Living near a trail corridor that is still changing raises practical questions about the closures, the timelines and what each project will leave behind. If you're weighing those questions for a home near the Capital Crescent Trail, Team Dajani is glad to talk them through with you.